How we test scene settings before handover

9 Sept 2026 · 4 min read

Our sequence for checking scenes, dimming range and control response on site, so the handover day has no surprises.

How we test scene settings before handover

Handover is the first time a client sees the lighting scheme in its final state, and the last practical moment to correct it. We treat it as a test rather than a demonstration.

Pass one: load by load

The first pass is load-by-load: every circuit is driven from 100% down to its lowest stable level to find flicker, drop-out and audible driver noise. This is done before any scene is recalled, so faults are isolated to a single fixture group.

Pass two: the scene list in real order

The second pass runs the scene list in the order a client would use it — arrival, working, dining, evening, night. Each scene is checked for balance across the room and for the transition speed between scenes.

Pass three: the control layer

The final pass is the control layer: keypads, app, sensors and voice, each tested on the actual network with the devices the client will use. Anything that needs a firmware update is resolved before the walkthrough rather than after.

Key points

  • Test each circuit from full output to its lowest stable level.
  • Run scenes in the order a client would actually use them.
  • Test controls on the client's own devices and network.